Strathcona County is upgrading Township Road 560 to a Class I road from Range Road 214 to approximately 1,200 metres east.  

The upgrades will provide a safe and sustainable roadway to help support current and future traffic and will tie into the improvements completed on Township Road 560 in 2018. 

Proposed upgrades include:

  • Widening the current 6.5 metre roadway to a 10 metre roadway (3.5 metre wide lanes and 1.5 metre wide shoulder) 
  • Improving the roadway to a hot-mix asphalt surface 
  • Providing gentler ditch side slopes, where possible 
  • Improving the road profile to prevent future road closures due to spring flooding 

Project timeline

This project is currently in the construction phase.

  • Fall 2023 to Summer 2024 – Power pole relocation work and jersey barrier removal to be completed.
  • Summer 2023 – Project roadwork substantially complete.
  • November 2022 – Roadway opened with majority of work completed. 
  • November 2021 – Roadway opened with temporary roadway shift.

Project contacts:

Transportation Engineering and Operations
Phone: 780-417-7100
Email: transportation@strathcona.ca

Contractor:
Kyle Baird, Project Manager
Noyen Construction Ltd.
780-237-7767

County Connect