Strathcona County is upgrading Township Road 560 to a Class I road from Range Road 214 to approximately 1,200 metres east. Â
The upgrades will provide a safe and sustainable roadway to help support current and future traffic and will tie into the improvements completed on Township Road 560 in 2018.Â
Proposed upgrades include:
- Widening the current 6.5 metre roadway to a 10 metre roadway (3.5 metre wide lanes and 1.5 metre wide shoulder)Â
- Improving the roadway to a hot-mix asphalt surfaceÂ
- Providing gentler ditch side slopes, where possibleÂ
- Improving the road profile to prevent future road closures due to spring floodingÂ
Project timeline
This project is currently in the construction phase.
- Fall 2023 to Summer 2024 – Power pole relocation work and jersey barrier removal to be completed.
- Summer 2023 – Project roadwork substantially complete.
- November 2022 – Roadway opened with majority of work completed.Â
- November 2021 – Roadway opened with temporary roadway shift.
Project contacts:
Transportation Engineering and Operations
Phone: 780-417-7100
Email: transportation@strathcona.ca
Contractor:
Kyle Baird, Project Manager
Noyen Construction Ltd.
780-237-7767